|
Kiwanis-Mary Hall Park was originally part of the 160 acres
homesteaded in 1892 by William and Mary Hall. In 1952 9.7 acres
was conveyed to the city with the stipulation that it only be
used as a park. Downtown and Westside Kiwanis Clubs teamed up to
complete the project; formed a committee in 1999. On September
16, 2002 then Mayor Jerry Munson signed an agreement to allow
the park to proceed.
MILESTONES:
Work began in 2001. Volunteers
hewed a nature trail along Lime Creek (the nature trail
was upgraded in 2003 because of plant incursion.)
Spring 2003 - A native plant area was begun in an effort
to enhance the numbers and kinds of native plants visitors could
enjoy. The park currently has over 100 different native and
introduced species.
Summer of 2003 - A learning platform with steps was
installed leading down to Lime Creek and ground was broken on
August 21, 2003, for Phase I, the shelter, of the Learning
Center. Construction was completed in November, 2003 and the
staining of the wood was completed in April, 2004.
Spring 2004 - Rapid City Fire Department personnel
accomplished a controlled burn on the native plant area to
remove dead vegetation and to help control the smooth brome
grass; 150 native plants were transplanted, a sign and brochure
box were added. Trenching and placement of sewer and water lines
was completed.
Spring 2005 - Over 100 additional native plants were
added to the native plant area. Oak and aspen trees were donated
and planted by volunteers. West Middle School eighth grade
science classes visited the park on several occasions. Their
first visit in 2005 was to determine what projects they
might accomplish and on the second visit they made a short path,
and placed stones in Lime Creek for crossing.
Spring 2006 - Kiwanis-Mary Hall Park was honored by the
Rapid City Urban Forestry Committee for the tree planting
efforts in the park. West Middle School science class students
helped clean up park areas, including Lime Creek, and later
joined adult volunteers in planting nearly 200 shrubs and
seedling trees. Plumbing the water into the shelter was
completed in the summer of 2006, allowing volunteers to save
approximately 90% of the transplants. |